HIGHWAY PROJECTS FOR 2011
09/10/10
T-335 E. Maple Street, from Plaza Drive to Apple Blossom Lane:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
2,325 35 9,042 1.5 814 $65,100
Curb Sealer, 52 gals. $310
Total for E. Maple Street $65,410
(Based on Asphalt at $80.00 per ton)
T-365, Summit Drive, from Brunswick Lane to end:
Scratch Coat and Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
Scratch Coat:
900 35 3,500 0.5 105 $8,400
Overlay:
1,035 35 4,025 1.5 362 $28,980
Curb Sealer, 26 gals. $156
Total for Summit Drive $37,536
(Based on Asphalt at $80.00 per ton)
T-337, Brunswick Lane, entire length:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
2,150 35 8,361 1.5 753 $60,200
Curb Sealer, 48 gals. $287
Total Brunswick Lane $60,487
(Based on Asphalt at $80.00 per ton)
T-356, Highland Drive, from W. Ridge Road to Clearview Drive:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
792 35 3,080 1.5 277 $22,176
Curb Sealer, 18 gals. $106
Total Highland Drive $22,282
(Based on Asphalt at $80.00 per ton)
T-355, North & South Clearview Drive, entire length:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
1,225 35 4,764 1.5 429 $34,300
Curb Sealer, 27 gals. $163
Total Clearview Drive $34,463
(Based on Asphalt at $80.00 per ton)
          Total for 2011 - $220,178
 
Budget Allocation:
            Liquid Fuels - 439.00 - $150,000
            County Aid $2,910
            Capital Reserve - 439.610 $67,268
Total $220,178
Added 04/25/11
T-342, S. Grant Street, Boro Line to E. Elm Street:
Overlay with 9.5mm
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
340 35 1322 1.5 119 $8,925
Curb Sealer, 8 gals. $45
Mill Curb Line
Length, (ft.) Width (ft.) Sq. Yds. $/Sq Yd
680 6 453 5 $2,267
Total S. Grant Street $11,237