| HIGHWAY PROJECTS FOR 2011 | |||||
| 09/10/10 | |||||
| T-335 E. Maple Street, from Plaza Drive to Apple Blossom Lane: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 2,325 | 35 | 9,042 | 1.5 | 814 | $65,100 |
| Curb Sealer, 52 gals. | $310 | ||||
| Total for E. Maple Street | $65,410 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-365, Summit Drive, from Brunswick Lane to end: | |||||
| Scratch Coat and Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| Scratch Coat: | |||||
| 900 | 35 | 3,500 | 0.5 | 105 | $8,400 |
| Overlay: | |||||
| 1,035 | 35 | 4,025 | 1.5 | 362 | $28,980 |
| Curb Sealer, 26 gals. | $156 | ||||
| Total for Summit Drive | $37,536 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-337, Brunswick Lane, entire length: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 2,150 | 35 | 8,361 | 1.5 | 753 | $60,200 |
| Curb Sealer, 48 gals. | $287 | ||||
| Total Brunswick Lane | $60,487 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-356, Highland Drive, from W. Ridge Road to Clearview Drive: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 792 | 35 | 3,080 | 1.5 | 277 | $22,176 |
| Curb Sealer, 18 gals. | $106 | ||||
| Total Highland Drive | $22,282 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-355, North & South Clearview Drive, entire length: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 1,225 | 35 | 4,764 | 1.5 | 429 | $34,300 |
| Curb Sealer, 27 gals. | $163 | ||||
| Total Clearview Drive | $34,463 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| Total for 2011 - | $220,178 | ||||
| Budget Allocation: | |||||
| Liquid Fuels - 439.00 - | $150,000 | ||||
| County Aid | $2,910 | ||||
| Capital Reserve - 439.610 | $67,268 | ||||
| Total | $220,178 | ||||
| Added 04/25/11 | |||||
| T-342, S. Grant Street, Boro Line to E. Elm Street: | |||||
| Overlay with 9.5mm | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 340 | 35 | 1322 | 1.5 | 119 | $8,925 |
| Curb Sealer, 8 gals. | $45 | ||||
| Mill Curb Line | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | $/Sq Yd | ||
| 680 | 6 | 453 | 5 | $2,267 | |
| Total S. Grant Street | $11,237 | ||||