HIGHWAY PROJECTS FOR 2010
09/22/2009
T-436, Lynnwood Drive from Ash Street to Park Drive:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
1,590 35 6,183 1.5 557 $44,520
Curb Sealer, 36 gals. $142
Total for Lynnwood Drive $44,662
(Based on Asphalt at $80.00 per ton)
T-464, Lynnwood Court:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
120 100 1,333 1.5 120 $9,600
Curb Sealer, 4 gals. $18
Total for Lynnwood Court $9,618
(Based on Asphalt at $80.00 per ton)
T-432, Holly Drive. from Ash Street. to Lynnwood Drive:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
845 35 3,286 1.5 296 $23,660
Curb Sealer, 19 gals. $75
Total Holly Drive $23,735
(Based on Asphalt at $80.00 per ton)
T-455, Holly Court:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
190 85 1,794 1.5 162 $12,920
Curb Sealer, 4 gals. $16
          Total Holly Court $12,936
(Based on Asphalt at $80.00 per ton)
T-438, Ash Street from Park Drive to Lynnwood Drive:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
265 35 1,031 1.5 93 $7,420
Curb Sealer, 6 gals. $24
          Total Ash Street $7,444
(Based on Asphalt at $80.00 per ton)
T-362, Mallard Point Drive from Park Drive to end:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
635 35 2,469 1.5 222 $17,780
Curb Sealer, 14 gals. $56
Total Mallard Point Drive $17,836
(Based on Asphalt at $80.00 per ton)
T-363, Mill Pond Way from Mallard Point Drive to Park Drive:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
950 35 3,694 1.5 333 $26,600
Curb Sealer, 21 gals. $84
Total Mill Pond Way $26,684
(Based on Asphalt at $80.00 per ton)
T-326, Sportsman Road from Old Forge Road to end:
Overlay with 9.5 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
800 24 2,133 2 256 $20,480
Curb Sealer, 0 gals. $0
Total Sportsman Road $20,480
(Based on Asphalt at $80.00 per ton)
T-441, East Ridge Road, between North Forge Rd and Naftzinger Rd:
Overlay with 19 mm.
Estimated
Length, (ft.) Width (ft.) Sq. Yds. Depth (in.) Tons Cost
2,340 22 5,720 2 686 $54,912
Curb Sealer, 0 gals. $0
Total East Ridge Road $54,912
(Based on Asphalt at $80.00 per ton)
          Total for 2010 - $218,307
 
Budget Allocation:
            Liquid Fuels - 439.00 - $150,000
            County Aid $2,910
            Capital Reserve - 439.610 $65,397
Total $218,307