| HIGHWAY PROJECTS FOR 2010 | |||||
| 09/22/2009 | |||||
| T-436, Lynnwood Drive from Ash Street to Park Drive: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 1,590 | 35 | 6,183 | 1.5 | 557 | $44,520 |
| Curb Sealer, 36 gals. | $142 | ||||
| Total for Lynnwood Drive | $44,662 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-464, Lynnwood Court: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 120 | 100 | 1,333 | 1.5 | 120 | $9,600 |
| Curb Sealer, 4 gals. | $18 | ||||
| Total for Lynnwood Court | $9,618 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-432, Holly Drive. from Ash Street. to Lynnwood Drive: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 845 | 35 | 3,286 | 1.5 | 296 | $23,660 |
| Curb Sealer, 19 gals. | $75 | ||||
| Total Holly Drive | $23,735 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-455, Holly Court: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 190 | 85 | 1,794 | 1.5 | 162 | $12,920 |
| Curb Sealer, 4 gals. | $16 | ||||
| Total Holly Court | $12,936 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-438, Ash Street from Park Drive to Lynnwood Drive: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 265 | 35 | 1,031 | 1.5 | 93 | $7,420 |
| Curb Sealer, 6 gals. | $24 | ||||
| Total Ash Street | $7,444 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-362, Mallard Point Drive from Park Drive to end: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 635 | 35 | 2,469 | 1.5 | 222 | $17,780 |
| Curb Sealer, 14 gals. | $56 | ||||
| Total Mallard Point Drive | $17,836 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-363, Mill Pond Way from Mallard Point Drive to Park Drive: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 950 | 35 | 3,694 | 1.5 | 333 | $26,600 |
| Curb Sealer, 21 gals. | $84 | ||||
| Total Mill Pond Way | $26,684 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-326, Sportsman Road from Old Forge Road to end: | |||||
| Overlay with 9.5 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 800 | 24 | 2,133 | 2 | 256 | $20,480 |
| Curb Sealer, 0 gals. | $0 | ||||
| Total Sportsman Road | $20,480 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| T-441, East Ridge Road, between North Forge Rd and Naftzinger Rd: | |||||
| Overlay with 19 mm. | |||||
| Estimated | |||||
| Length, (ft.) | Width (ft.) | Sq. Yds. | Depth (in.) | Tons | Cost |
| 2,340 | 22 | 5,720 | 2 | 686 | $54,912 |
| Curb Sealer, 0 gals. | $0 | ||||
| Total East Ridge Road | $54,912 | ||||
| (Based on Asphalt at $80.00 per ton) | |||||
| Total for 2010 - | $218,307 | ||||
| Budget Allocation: | |||||
| Liquid Fuels - 439.00 - | $150,000 | ||||
| County Aid | $2,910 | ||||
| Capital Reserve - 439.610 | $65,397 | ||||
| Total | $218,307 | ||||